Clatterbridge Hospital Cancer Centre CHP

View PDF

HEADLINES

2 miles of prefabricated stainless steel pipework

9 metre long pipe bridge fabricated offsite

90% of the scheme was fabricated offsite

8 weeks to install

Rooftop and subterranean working in a live hospital environment

Project TitleClatterbridge Hospital Cancer Centre CHP
LocationWirral
Value£480,000
Duration12 weeks (four weeks prefab, eight weeks installation onsite)

OVERVIEW

We managed the entire pipework installation for the 1.5MW combined heat and power package for this large-scale, live hospital environment.

A 16-strong team of engineers, welders, site supervisors and project managers delivered the scheme with works including design, fabrication, offsite checking, delivery, installation, connection and onsite testing.

CHALLENGE

It was a sensitive location given it is a cancer centre so great consideration was given to working in and around the site at all times.

Regular and detailed liaison with each hospital department was a key feature of our work. At times we were installing and constructing on roofs and access was often difficult.

Conversely, there was a significant element of subterranean pipework installed requiring us to overcome obstacles to connect vital components.

SOLUTION

We ran a 150mm flow and returned district mains to seven individual plant rooms. In total, we prefabricated two miles of stainless steel pipework as well as the offsite fabrication of a nine-metre-long pipe bridge, which spanned a critical access road for the A&E department.

Data for the project showed 90% of the pipework installed was fabricated offsite.

RESULTS

Crucial to the success of the scheme was a high level of planning and communication with the client’s project team, which ensured the works were delivered on time and defect-free.