University of Leeds: School of Fine Art

View PDF

HEADLINES

Modern day building services retrofitted in a facility constructed in 1930

Overcame a mid-programme redesign of the mechanical plant

3 weeks extension to overcome the weak roof structure

Re-used steam generated from the plant room boiler house as the primary heat source

Project TitleUniversity of Leeds: School of Fine Art
ClientUniversity of Leeds
ContractorSewell Construction
Duration32 weeks
Value£1.2 million
LocationLeeds

“G&H carried out the mechanical and electrical installation on this project and, as in previous projects I’ve worked on with them, they were very proactive and user friendly. The quality of their work is very good.”

Mark Dodgson, Project Manager, Sewell Construction

OVERVIEW

This intricate scheme saw us retrofit modern day building services into a Grade II listed facility constructed in 1930. The University of Leeds’ Old Mining Building spans four storeys including an extension that was added in the 1970s and required a complete fit out as it underwent a change of use.

CHALLENGE

We worked closely with Sewell Construction and a conservation officer to retain as many of the building’s existing features. With such an old building, walls were not true and straight so feeding pipework and power was problematic but we overcame this by stripping back the walls to the source and rebuilding.

The mechanical plant was initially designed to be installed on the roof but we were subsequently informed there was too much weight for the building to bear. We were on-site at this stage and had to redesign a crucial part of the scheme and retrofit the heat recovery unit inside the existing building with some of the ductwork being fed through windows.

This presented different challenges: firstly, it meant a redesign of other internal features affected by the change, requiring us to use more natural ventilation. Secondly, it impacted on our timetable of works resulting in an extension of three weeks giving us a short period of time to stay on programme.

Other challenges included creating a building conducive to inspiring students who require space to display works in an aesthetically pleasing form so many services were concealed allowing for cleaner lines.

SOLUTION

The long-term sustainability of the building was of paramount importance in our designs and included re-using the steam generated in the plant room boiler house as the primary source of heat, LED lighting and natural ventilation.

RESULTS

The project was successfully delivered on time. Modern services were integrated without compromising the building’s character, supporting both sustainability goals and the functional needs of the School of Fine Art, History of Art and Cultural Studies.