Steeper Group new HQ (Leeds)

View PDF

HEADLINES

Full M&E design and build

Met a tight deadline of just five months

Worked in partnership with the main contractor and client

Bespoke services to meet office, factory, manufacturing and customer areas

Existing industrial unit converted into a new centre of excellence

Project TitleSteeper Group new HQ (Leeds)
ClientSteeper Group
ContractorSewell Construction
Duration20 weeks
Value£800,000

“Partnership is a term which is often used in our industry but sadly isn’t always backed up with actions however on Steeper our work with G&H represented a true partnership.

After G&H formed an introduction to the client team on Steeper who were seeking a construction partner, G&H and Sewell worked on an open book basis, developing the costs and design together as part of the project team to achieve an early commencement date.

The industrial nature of Steeper’s new facility meant that all services were exposed and suspended above the working area.

As such the quality of G&H’s installation on site couldn’t disappoint and it certainly didn’t, delivering a superb building services installation which has truly changed the way Steeper operate as a business.”

Josh Donnelly, Development Manager, Sewell Construction

OVERVIEW

Steeper Group is one of the leading prosthetics, orthotics and assistive technology companies.

It has approximately 110 state-registered clinicians and 194 technicians providing clinical services to some 250,000 patients every year across prosthetics and orthotics.

It is also one of the UK’s largest suppliers of orthotic and orthopaedic products to the NHS.

CHALLENGE

After falling victim to the Christmas floods in 2015, it brought its manufacturing and office headquarters together creating a new, £2 million state-of-the-art facility for 200 members of staff.

SOLUTION

Working in partnership with the main contractor, Sewell Construction, we carried out a full mechanical and electrical design and build scheme to convert an existing industrial unit into a new centre of excellence in just five months.

Detailed design sessions at the preconstruction phase saw us working closely with Steeper Group to ensure every part of the facility was bespoke to meet the client’s needs and drive efficiencies.

The building services were designed to accommodate the specialist requirements of the manufacturing equipment throughout the space.

RESULTS

The result is a facility that has the best modern day building services that create the perfect environment for Steeper Group to operate in.

The scheme was delivered on time and on budget.